Package # VB-S-C-2019-20 QBE Nomination Closing Date
Title Sag and Ball Mill Reline Tender Issue Date TBA
    Bid Closing Date TBA

For more information contact: Dwayne Chiasson
709-896-6426
709-752-3459
click here to send email

Contract Scope

1.1.    Performance of the Work shall be completed in accordance with the following schedule:

2.1.1.         Contract Start: May 2019

      1. Contract Complete: Aug 2024

         

3.       Scope

    1. Detailed Scope of Work to be performed by the Contractor shall include the following:

      1. Contractor to provide qualified labour supervision and maintenance personnel with extensive experience in Concentrator Ball Mill and Sag Mill relining. Services to include but not limited to; installation, technical recommendation, and planning to minimize the risk of future repairs, maximize efficiency and minimize down time. 

      2. Ball Mill Manufacture is Outokumpu Serial#03-12- BM

      3. SAG Mill is Manufacture is Outokumpu  Serial#03-013-SAG

      4. Maintenance service personnel to work shifts – days and nights as required for completion with timeline. Typical shift is two 12HR shifts/day 7 days/week or as directed by Company.

      5. Exactly Liner change schedule and scope to be determined by Vale, however technical recommendation from vendor after each visit to be included with service report.

      6. Contractor to submit a service report detailing all maintenance activities performed during the major shutdowns.  Report must include recommendations, findings, suggested maintenance and future actions to improve reliability and reduce time lines for installation of liners.

      7. The contractor shall take its day to day direction from the Company’s Maintenance management designate.

      8. All torque specs required to be confirmed with Vale maintenance before commencement of reline.

      9. Work to be performed onsite at Voisey’s Bay Mine Site

      10. All supervisors/technicians are required to have Newfoundland and Labrador specific fall arrest and confined space training prior to mobilizing to site if required to perform the work.