Package # VB-S-C-2018-3 QBE Nomination Closing Date
Title NDT X Ray requirements Tender Issue Date TBA
    Bid Closing Date TBA

For more information contact: Dwayne Chiasson
709-896-6426
709-752-3459
click here to send email

Contract Scope


1.     general


    1. Without limiting the generality of the foregoing, the Work to be provided by the Contractor shall include the provision of all management, supervision, administration, technical expertise and support, skilled labour, materials, consumables, equipment, services, tools, and each and every item of expense necessary, other than that stipulated in the Contract Documents as provided by the Company, to complete the Work of this Contract.



2.     ScHEDULE


2.1.    Performance of the Work shall be in accordance with the following schedule:


2.1.1.         Work Start: 1 JAN 2018


      1. Work Complete: 1 JAN 2021

         


3.        Scope


Detailed Scope of Work to be performed by the Contractor shall include the following:


    1. To be performed by service personnel certified, trained and qualified in the method of testing required, which could include: eddy current, magnetic, penetrant, radiographic and ultrasonic testing.

    2. Perform specified testing at selected areas throughout the mine site which will be determined with individual site visit work scopes.

    3. Scope of work may include, but is not limited to, X-Ray NDT on Tailings pipelines, X-Ray NDT on Sag Mill and Ball Mill shell, X-Ray NDT on Crusher Spider, Magnetic Flux Leakage tank inspections, etc.

    4. The Contractor shall have personnel who are certified to API 653 tank inspection.

    5. The Contractor shall have personnel who are CWB certified.

    6. The Contractor shall have personnel who are NACE certified to perform corrosion and coatings inspections.

    7. The Contractor shall be able to provide inspection and an engineer’s certification of lifting devices as required.

    8. The Contractor shall be able to provide advanced vibration analysis diagnostics as required by the site.

    9. Preliminary report to be submitted within one week of completion of the specific site visit work scope.

       


4.      COMPANY FURNISHED SERVICES & FACILITIES


The Company will provide the Contractor, at no cost, specifically for the performance of the Work of this Contract, the following Services and Facilities:


    1. As per general contract

    2. Full access to assisting personnel and transportation to perform service activities.



  1. Company furnished equipment & tools

                The Company will provide the Contractor, at no cost, specifically for the performance of the Work of this Contract, the following Equipment and Tools:


    1. The Contractor will provide own hand tools required to perform maintenance activities.

    2. The Contractor will supply all testing equipment and required consumables to complete the site specific work scope.



 


6.    COMPANY FURNISHED CONSUMABLES & MATERIALS


The Company will provide the Contractor, at no cost, specifically for the performance of the Work of this Contract, the following Equipment and Tools:


  1.  

  2.  

  3.  

  4.  

  5.  

  6.  

    1. The company will provide consumables as per the general contract.